03 / 10Worked example

Scale estimates

Why do 540 autosave opportunities not guarantee that many writes?

An autosave opportunity produces a write only when needed.

Starting point Check unchanged answers and bundling.

Assumptions for the example case

Illustrative design: 50,000 attempts per day, 10,000 simultaneous starts, a 90-minute duration, autosave every 10 seconds and a peak of 1,000 answer writes/s. This gives at most 540 save opportunities per attempt open for the full duration; actual writes depend on changes and batching.

Load model

Distinguish the daily average, simultaneous starts and peak write rate.

Calculations

  1. 01

    Attempts

    0.579/s

    50,000 ÷ 86,400

    For the designThe daily average does not represent the load of a scheduled exam session.

  2. 02

    Autosave opportunities

    540 per attempt

    5,400 s ÷ 10 s

    For the designOnly changes should create a write.

  3. 03

    Peak write rate

    1000/s

    Predefined test assumption

    For the designMeasure conflict and latency separately.

Terms in this step

Opportunity
Possible trigger, the actual effect of which depends on changes.

Try it yourself

Calculate 540 opportunities for 10,000 attempts.

A hint for your attempt

This is an upper limit before change filtering.

Compare with a possible solution
Opportunities
5,400,000.
Writes
The number of writes must be measured or estimated with additional assumptions.

Apply to your project

Define a change rate as a new assumption.

Interfaces carry version and reception time.