Construction change orders, drawing revisions and cost impact

A new drawing revision is submitted while a change order awaits approval. An approval screen opened earlier must not approve the new scope of work.

Follow the design
Unfinished building model next to construction plan and modification document.

Participants and responsibilities

Roles and responsibilities

A new drawing revision is submitted while a change order awaits approval. An approval screen opened earlier must not approve the new scope of work.

  • Contractors

    Submit changes to the scope of work and costs.

  • Construction management

    Checks drawing references and execution.

  • Approvers

    Confirm the specific change-order scope.

  • Cost control

    Maintains approved cost snapshots.

  • Platform operations

    Secures document access and transmission.

Workflow in detail

From request to documented result

Each step shows the action of the person, the task of the system and the achieved result.

  1. Describe the change

    Action
    Contractors: describe the change.
    What the system does
    Binds the work to the relevant immutable drawing revision.

    Result: The change in scope is traceable.

  2. Link the drawing revision

    Action
    Construction management: link the drawing revision.
    What the system does
    Describes the additional agreed work.

    Result: The affected drawing revision is identified.

  3. Review costs

    Action
    Cost control: review costs.
    What the system does
    Calculates the submitted line items traceably.

    Result: The cost revision is traceable.

  4. Approve the scope

    Action
    Approvers: approve the scope.
    What the system does
    Binds the required approval to the drawing, scope of work and costs.

    Result: Approval binds the exact scope.

  5. Document implementation

    Action
    Construction management: document implementation.
    What the system does
    Links the confirmed result to the existing history and shows remaining open issues.

    Result: Implementation is documented.

Workflow variations

Clear reactions to deviations

Discrepancies remain visible together with the responsible role and the next evidence required.

New drawing revision

A drawing change arrives during approval.

Reaction
Construction management assigns the change to a new revision requiring review.
Result
The existing approval remains limited to the old scope.

Second approval missing

The internal cost threshold requires an additional approval.

Reaction
Approvers obtain the additional review decision.
Result
The change order remains open until then.

Implementation discrepancy

The completed work differs from the approved scope.

Reaction
Construction management documents the discrepancy and determines the follow-up order.
Result
The completion record describes the actual outcome.
Open design steps