System Design Atlas

Construction change orders, drawing revisions and cost impact

01 / 10Worked example

Purpose and boundary

What responsibility does the change order API assume, and which evidence originates outside the system?

The initial assumptions define responsibility in this example. We follow change order N-32, drawing revision P-32 and cost revision K-32. These stable identifiers connect the technical views. A new drawing revision arrives while a change order awaits approval. An earlier approval screen must not approve the new scope. The fictional internal workflow uses frozen drawing and cost snapshots.

Starting point A new drawing revision is submitted while a change order awaits approval. An approval screen opened earlier must not approve the new scope of work.

Assumptions for the example case

Original fictional design: an internal approval workflow for a change order with frozen drawings and costs. The illustrative internal threshold is 500000 cents. Up to and including this amount, one approver is sufficient; above it, this case requires a second approver. All figures and test targets are illustrative assumptions.

Responsibilities and external boundary

Context · Change-order system

ContractorsChange order and scope of work
External drawing archiveImmutable drawing hash
Construction change order APIApproval binds the drawing revision, scope of work and cost revision.
Auftragnehmende → Nachtrags-APIScope of work and costs
Externes Planarchiv → Nachtrags-APIStable drawing reference
Nachtrags-API → AuftragnehmendeAcceptance or conflict

Approval binds the drawing revision, scope of work and cost revision.

A new drawing revision arrives while a change order awaits approval. An earlier approval screen must not approve the new scope. Actors sit outside the system boundary and the change order API sits inside it; the drawing archive has its own external boundary.

The specific design scope

Example situation
A new drawing revision is submitted while a change order awaits approval. An approval screen opened earlier must not approve the new scope of work.
Scope
A fictional internal approval workflow for a change order with a frozen set of drawings and costs.
Excluded tasks
Legal assessment of claims, contract interpretation, billing rules and automatic commissioning of real construction work.

Approval binds an immutable scope of work

Approval binds an immutable scope of work

Approval binds an immutable scope of work.

A new drawing revision is submitted while a change order awaits approval. An approval screen opened earlier must not approve the new scope of work.

A fictional internal approval workflow for a change order with frozen drawings and costs. The exercise specifies the input and expected result.

Alternative considered
Extending the scope to legal claims assessment, contract interpretation, billing regulations or automatic commissioning of real construction work requires additional domain contracts.
Trade-off
The initial scope covers a fictional internal approval workflow for a change order with frozen drawings and costs.
Reassess
A need for legal claims assessment, contract interpretation, billing regulations or automatic commissioning of real construction work calls for a new scope decision.

Try it yourself

Assign responsibility for the change order, drawing archive and completion decision. Name one task outside the system boundary.

A hint for your attempt

Use the business guarantee and the explicitly limited scope.

Compare with a possible solution
Primary responsibility
The change order API maintains the authoritative change-order record. Construction management handles the business work; platform operations provides technical processing.
External boundary
The drawing archive remains an external evidence source. Legal claims assessment, contract interpretation, billing regulations and automatic commissioning of real construction work are outside the scope.

Apply to your project

Which evidence for a change order would originate outside the application in your own project?

Next: the cost threshold explicitly defines equality.