System Design Atlas

Water leak detection and repair orders

09 / 10Worked example

Operations and security

Who owns remedial work when measurements remain abnormal?

Monitoring signals need owners, responses and closure evidence. Field service handles domain investigation according to the role contract; technical recovery is coordinated with platform operations where that role is specified.

Starting point Separate measurement age from ingestion throughput.

Assumptions for the example case

This fictional worked design assumes a bounded metering zone, minute-by-minute flow readings, manual confirmation of findings and one active repair order per confirmed finding. Numbers and quality targets are illustrative test assumptions. Automatic valve control, full hydraulic simulation and drinking water quality assessment are outside scope.

Signal, ownership and resolution

Measurement ingestion, finding assessment and field evidence

Measurements delayedSignal
Measurements delayed → Platform operationscheck
Platform operationsBacklog cleared
Suspicion unresolvedSignal
Suspicion unresolved → Control roomcheck
Control roomFindings documented
Post-repair measurements missingSignal
Post-repair measurements missing → Field servicecheck
Field serviceInspection evidenced

Platform operations keeps ingestion stable; the control room investigates the finding; field service supplies work and post-repair inspection evidence.

Flow remains abnormal after repair. Field service receives the outstanding reason for remedial work. The finding stays open until evidence resolves it.

Access and recovery

Object-level authorisation
The control room receives only objects required for its task. The server checks each change against the role and specific object. Field service receives documented investigation permissions.
Evidence rather than assumption
Field service documents a repair offline and synchronises twice. One work record is created; the order stays in repariert until post-repair inspection provides evidence. Missing measurements after repair leave verification open rather than proving successful restoration.
Operating agreement
Agree retention periods, on-call coverage, recovery time and acceptable data loss before live operation. Test restoration from backup using the open case from step 7. Keep sensitive payloads out of operational logs.

Assign responsibility for remedial work

Assign responsibility for remedial work

Give field service the reason for outstanding remedial work.

Flow remains abnormal after repair.

The finding stays open until evidence resolves it.

Alternative considered
Closing based on elapsed time conceals a remaining leak.
Trade-off
Worklists remain filled longer.
Reassess
Recurring causes require network planning.

Terms in this step

Assign responsibility for remedial work
The finding stays open until evidence resolves it.

Try it yourself

The reading sequence remains abnormal after repair. Who receives which work assignment, and when does it end?

A hint for your attempt

Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.

Compare with a possible solution
First part of the solution
Field service receives follow-up work with findings and repair reference.
Second part of the solution
Evidenced restoration or a documented alternative cause resolves the investigation; a timer does not.

Apply to your project

Which corresponding assumption in your project would you check first? Consider this trigger: Recurring causes require network planning.

Step 10 examines: test duplicate reports.