System Design Atlas

Agricultural field operations

05 / 10Worked example

Authoritative data and states

Which area limit remains relevant for a historical work record?

The interfaces require an authoritative state. A work record remains tied to the actual area boundary and machine used. A central revocation is only effective offline after device confirmation or expiry of the start-authorisation period. Actual area is not replaced by planned area. The following table separates current states from the evidence of their formation.

Starting point Compare the device sequence and content together.

Assumptions for the example case

Our own fictitious example design: Mechanical tillage of a field; a machine order; offline stored work record; local inspection of operational windows and approval. Figures and quality goals are illustrative test assumptions. Outside are plant protection product application, autonomous driving control, agronomic advice and payroll.

Data relationships and permitted transitions

Planned polygon, travelled track and remaining area

F-141 · G-412 ha planned polygon
E-141M-141 · 06–12
Work record8 ha in fact
Residual area4 ha open
freigegeben → lokal_übernommen → begonnenbegonnen → unterbrochen / arbeit_beendetarbeit_beendet → abgeglichen

The plan covers 12 ha in G-4; the documented track covers 8 ha; the remaining 4 ha needs separate planning.

The planned field area will be remeasured later. Bind work record to G-4. The area worked at that time remains explainable.

Entities and relationships

EntityAuthoritative dataResponsibility
Area F-14112 ha, boundary version G-4Geometry is versioned.
Operation E-141Machine, activity, time windowCombines planning and actual work.
Order A-141Signed content, start deadline, device allocationA bounded work authorisation usable offline.
Work recordDevice, sequence, sub-area, start, endDescribes actual work.
Weather forecastCreation time, area, valuesPlanning assistance; on-site inspection remains necessary.

Area F-141

Authoritative data
12 ha, boundary version G-4
Responsibility
Geometry is versioned.

Operation E-141

Authoritative data
Machine, activity, time window
Responsibility
Combines planning and actual work.

Order A-141

Authoritative data
Signed content, start deadline, device allocation
Responsibility
A bounded work authorisation usable offline.

Work record

Authoritative data
Device, sequence, sub-area, start, end
Responsibility
Describes actual work.

Weather forecast

Authoritative data
Creation time, area, values
Responsibility
Planning assistance; on-site inspection remains necessary.

Permitted state transitions

Starting pointTargetCondition
geplantfreigegebenMachine and field assigned without conflict.
freigegebenLocal_AcquiredThe device stores a complete order.
Local_AcquiredStartedStaff shall confirm on-site inspection before the start deadline.
StartedunterbrochenConditions prevent safe continuation.
Started or interruptedarbeit_beendetThe area actually worked is documented.
arbeit_beendetabgeglichenCentral checks evidence and open remaining area.
freigegebenwiderrufenDevice confirms revocation before the start; without confirmation, the start option remains visible as a risk until the deadline.

geplant

Target
freigegeben
Condition
Machine and field assigned without conflict.

freigegeben

Target
Local_Acquired
Condition
The device stores a complete order.

Local_Acquired

Target
Started
Condition
Staff shall confirm on-site inspection before the start deadline.

Started

Target
unterbrochen
Condition
Conditions prevent safe continuation.

Started or interrupted

Target
arbeit_beendet
Condition
The area actually worked is documented.

arbeit_beendet

Target
abgeglichen
Condition
Central checks evidence and open remaining area.

freigegeben

Target
widerrufen
Condition
Device confirms revocation before the start; without confirmation, the start option remains visible as a risk until the deadline.

Preserve the field boundary version

Preserve the field boundary version

Bind the work record to G-4.

The planned field area will be remeasured later.

The area worked at that time remains explainable.

Alternative considered
Applying current geometry retroactively would misrepresent the work performed.
Trade-off
Several borders remain stored.
Reassess
Retention requires limited archive strategy.

Terms in this step

Preserve the field boundary version
The area worked at that time remains explainable.

Try it yourself

F-141 is surveyed again after the operation. Which geometry explains the historical work record?

A hint for your attempt

Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.

Compare with a possible solution
First part of the solution
The proof remains bound to G-4, because this limit applied during use.
Second part of the solution
The new boundary version applies to new planning and does not overwrite the historical area allocation.

Apply to your project

Which corresponding assumption in your project would you check first? Use as an occasion: Retention requires a limited archive strategy.

Step 6: Keep local operations functional.