Purpose and system boundary
What local responsibility remains in case of failure of the platform connection?
Equipment A-81 has 50 kW of agreed dispatchable power. Dispatch F-81 requests a 20 kW reduction from 12:00 to 12:15 UTC. Control command C-81 carries generation 8 and the same scope. Measurement M-81 must be at most 30 s old to justify new dispatch planning. The example covers controllable equipment with an agreed power range, 15-minute dispatch, UTC time windows, local safety limits and measured effects.
Starting point The connection to the platform can be disconnected.
Assumptions for the example case
A fictional design with controllable equipment and an agreed power range; 15-minute dispatch; UTC time windows; local safety limits and measured effects. Figures and quality targets are illustrative test assumptions. Protection systems, primary frequency control, market bids and evidence of specific energy-regulation compliance remain outside its scope.
Context and responsibilities
Dispatch, local control and measured effect
Flexibility platform
Command acceptance and actual kW effect require separate evidence; local safety takes priority.
Assumptions for the worked example
- Scope
- Controllable equipment with an agreed power range; 15-minute dispatch; UTC time windows; local safety limits and measured effects.
- Possible extensions
- Protection systems, primary frequency control, market bids and evidence of specific energy-regulation compliance.
Preserve local safety
Enforce equipment limits and safe fallback behaviour locally.
The connection to the platform can be disconnected.
An expired remote order may not retain a lasting effect.
- Alternative considered
- A cloud decision for every safety action depends on connectivity.
- Trade-off
- Local rules require coordinated commissioning.
- Reassess
- Another asset class changes the protection requirements.
Terms in this step
- Preserve local safety
- An expired remote order may not retain a lasting effect.
Try it yourself
C-81 is running when the connection fails. Identify where expiry and local limits are enforced.
A hint for your attempt
Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.
Compare with a possible solution
- First part of the solution
- The plant control system checks the local end of validity and safety limits.
- Second part of the solution
- From 12:15, the agreed safe fallback rule takes over even without platform connectivity; a cloud timeout does not replace it.
Apply to your project
Which corresponding assumption would you check first in your project when a different equipment class changes safety requirements?