Change commands and retries
How do generation and validity windows prevent delayed control effects?
Scale alone does not ensure consistent retry behaviour. This proposed API binds the role, business object, change payload and expected state to each new intent. An idempotency key identifies the same intent after a response is lost.
Starting point Multiply 20 kW by 0.25 h to obtain 5 kWh.
Assumptions for the example case
A fictional design with controllable equipment and an agreed power range; 15-minute dispatch; UTC time windows; local safety limits and measured effects. Figures and quality targets are illustrative test assumptions. Protection systems, primary frequency control, market bids and evidence of specific energy-regulation compliance remain outside its scope.
Retries and new intent
Control contract · identity, generation, kW and expiry
An identical C-81 confirms the same acceptance; a changed setpoint conflicts and generation 7 has no effect.
Proposed domain API contracts
- POST
/flexibility-callsReserve agreed power capacity.
- Input
- Grid operations, A-81, 20 kW, interval [12:00,12:15) UTC, rationale, expected availability and key.
- Result
- F-81 with atomic power limitation; overbooking or unusable current measurement is rejected.
- Retry behaviour
- An identical operation by the same authorised role on the same object, using the same key and canonical payload, returns the stored original result. A changed payload under that key is rejected. External result identifiers are durably deduplicated after authentication; new intents check the current version again.
- POST
/plant-commandsTransmit a time-limited control command.
- Input
- Authenticated adapter, C-81, F-81, A-81, generation 8, power 20 kW, start, exclusive end and authorisation evidence.
- Result
- Local acceptance or rejection by generation, time and asset limits; receipt does not yet confirm any effect.
- Retry behaviour
- An identical operation by the same authorised role on the same object, using the same key and canonical payload, returns the stored original result. A changed payload under that key is rejected. External result identifiers are durably deduplicated after authentication; new intents check the current version again.
- POST
/measurementsAccept observed power measurements.
- Input
- Measurement source, M-81, A-81, measurement time, reception time, kW value, quality and event key.
- Result
- Durable observation; age over 30 s prevents new dispatch based on this value. Effect assessment remains separate.
- Retry behaviour
- An identical operation by the same authorised role on the same object, using the same key and canonical payload, returns the stored original result. A changed payload under that key is rejected. External result identifiers are durably deduplicated after authentication; new intents check the current version again.
- GET
/plant-commands/{id}Reconcile an existing command.
- Input
- Authorised equipment adapter, C-81 and generation.
- Result
- Documented local acceptance/expiration status; measured effect is reported separately.
- Retry behaviour
- Repeating a read creates no business effect; the returned current state may change between requests.
Time-limit commands
Check the generation and expiry locally.
A delayed order reaches the plant.
Old or expired orders do not have a retroactive effect.
- Alternative considered
- Relying only on arrival order may favour an old command.
- Trade-off
- Clocks and generations need a verified contract.
- Reassess
- Time deviations exceed the agreed tolerance.
Terms in this step
- Time-limit commands
- Old or expired orders do not have a retroactive effect.
Try it yourself
Generation 7 arrives after generation 8. Generation 8 is then repeated with a changed setpoint value. Predict both answers.
A hint for your attempt
Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.
Compare with a possible solution
- First part of the solution
- Generation 7 remains ineffective as obsolete.
- Second part of the solution
- Generation 8 with changed content causes a conflict. A changed dispatch requires a new command that explicitly replaces the old one.
Apply to your project
Which corresponding assumption would you check first in your project when clock deviations exceed the agreed tolerance?