Authoritative data and states
How are concurrent dispatches checked against limited power capacity?
The interfaces require an authoritative state. Only the newest valid control command may take effect within its time window. Local equipment limits take precedence. An acknowledgement does not establish delivered kW. The table separates current states from evidence of how they arose.
Starting point Check the generation and expiry locally.
Assumptions for the example case
A fictional design with controllable equipment and an agreed power range; 15-minute dispatch; UTC time windows; local safety limits and measured effects. Figures and quality targets are illustrative test assumptions. Protection systems, primary frequency control, market bids and evidence of specific energy-regulation compliance remain outside its scope.
Data relationships and permitted transitions
Equipment, dispatch, control command, measurement and effect
F-81 describes the request, C-81 its validity at the equipment, and M-81 the observed measurements over time.
Entities and relationships
| Entity | Authoritative data | Responsibility |
|---|---|---|
| Equipment A-81 | Power range, local limits, availability | Produces the physical effect. |
| Dispatch F-81 | 20 kW, time window, justification | Requires a time-limited effect. |
| Control command C-81 | Generation 8, setpoint, start, expiry | Old generations are rejected locally. |
| Measurement M-81 | Measuring time, receiving time, unit kW, quality | Records an observation, not command acceptance. |
| Evidence of effect | Dispatch reference, measurement period, assessment rule | Distinguishes accepted commands from verified effects. |
Equipment A-81
- Authoritative data
- Power range, local limits, availability
- Responsibility
- Produces the physical effect.
Dispatch F-81
- Authoritative data
- 20 kW, time window, justification
- Responsibility
- Requires a time-limited effect.
Control command C-81
- Authoritative data
- Generation 8, setpoint, start, expiry
- Responsibility
- Old generations are rejected locally.
Measurement M-81
- Authoritative data
- Measuring time, receiving time, unit kW, quality
- Responsibility
- Records an observation, not command acceptance.
Evidence of effect
- Authoritative data
- Dispatch reference, measurement period, assessment rule
- Responsibility
- Distinguishes accepted commands from verified effects.
Permitted state transitions
| Starting point | Target | Condition |
|---|---|---|
| geplant | angenommen | Plant control confirms valid order. |
| geplant | abgelehnt | Power, timing or a local limit conflicts with the command. |
| angenommen | wirksam | Appropriate valid measurement proves the agreed effect. |
| angenommen | wirkung_unbekannt | Measurement is missing or unusable. |
| wirksam or wirkung_unbekannt | beendet | Expiry reached; the local safe fallback rule takes over. |
| beendet | abgeschlossen | Effect evidence or a documented investigation outcome is available. |
geplant
- Target
- angenommen
- Condition
- Plant control confirms valid order.
geplant
- Target
- abgelehnt
- Condition
- Power, timing or a local limit conflicts with the command.
angenommen
- Target
- wirksam
- Condition
- Appropriate valid measurement proves the agreed effect.
angenommen
- Target
- wirkung_unbekannt
- Condition
- Measurement is missing or unusable.
wirksam or wirkung_unbekannt
- Target
- beendet
- Condition
- Expiry reached; the local safe fallback rule takes over.
beendet
- Target
- abgeschlossen
- Condition
- Effect evidence or a documented investigation outcome is available.
Reserve flexibility
Check overlapping commitments against availability atomically.
30 and 40 kW compete for 50 kW.
The second commitment does not go beyond the scope.
- Alternative considered
- Independent planning lists overbook the plant.
- Trade-off
- Time window checks are becoming more complex.
- Reassess
- Many partial retrievals justify an extended model.
Terms in this step
- Reserve flexibility
- The second commitment does not go beyond the scope.
Try it yourself
Reserve 30 and 40 kW concurrently from 50 kW. State the outcome in both orders and the remaining capacity.
A hint for your attempt
Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.
Compare with a possible solution
- First part of the solution
- 30 kW first: 20 kW remain, 40 kW is rejected.
- Second part of the solution
- 40 kW first: 10 kW remain, 30 kW is rejected. A simultaneous promise of 70 kW violates the rule.
Apply to your project
Which corresponding assumption would you check first in your project when many partial dispatches justify a richer model?