System Design Atlas

Electricity grid flexibility dispatch

05 / 10Worked example

Authoritative data and states

How are concurrent dispatches checked against limited power capacity?

The interfaces require an authoritative state. Only the newest valid control command may take effect within its time window. Local equipment limits take precedence. An acknowledgement does not establish delivered kW. The table separates current states from evidence of how they arose.

Starting point Check the generation and expiry locally.

Assumptions for the example case

A fictional design with controllable equipment and an agreed power range; 15-minute dispatch; UTC time windows; local safety limits and measured effects. Figures and quality targets are illustrative test assumptions. Protection systems, primary frequency control, market bids and evidence of specific energy-regulation compliance remain outside its scope.

Data relationships and permitted transitions

Equipment, dispatch, control command, measurement and effect

Equipment A-8150 kW agreed
A-81 → F-811:n dispatches
Dispatch F-8120 kW · 15 min
F-81 → C-811:n generations
Control command C-81Generation 8
M-81 → F-81Evidence of effect
Measurement M-81Time + Unit + Quality
geplant → angenommen / abgelehntangenommen → wirksam / wirkung_unbekannt→ beendet → abgeschlossen

F-81 describes the request, C-81 its validity at the equipment, and M-81 the observed measurements over time.

30 and 40 kW compete for 50 kW. Check overlapping commitments against availability atomically. The second reservation must stay within the remaining capacity.

Entities and relationships

EntityAuthoritative dataResponsibility
Equipment A-81Power range, local limits, availabilityProduces the physical effect.
Dispatch F-8120 kW, time window, justificationRequires a time-limited effect.
Control command C-81Generation 8, setpoint, start, expiryOld generations are rejected locally.
Measurement M-81Measuring time, receiving time, unit kW, qualityRecords an observation, not command acceptance.
Evidence of effectDispatch reference, measurement period, assessment ruleDistinguishes accepted commands from verified effects.

Equipment A-81

Authoritative data
Power range, local limits, availability
Responsibility
Produces the physical effect.

Dispatch F-81

Authoritative data
20 kW, time window, justification
Responsibility
Requires a time-limited effect.

Control command C-81

Authoritative data
Generation 8, setpoint, start, expiry
Responsibility
Old generations are rejected locally.

Measurement M-81

Authoritative data
Measuring time, receiving time, unit kW, quality
Responsibility
Records an observation, not command acceptance.

Evidence of effect

Authoritative data
Dispatch reference, measurement period, assessment rule
Responsibility
Distinguishes accepted commands from verified effects.

Permitted state transitions

Starting pointTargetCondition
geplantangenommenPlant control confirms valid order.
geplantabgelehntPower, timing or a local limit conflicts with the command.
angenommenwirksamAppropriate valid measurement proves the agreed effect.
angenommenwirkung_unbekanntMeasurement is missing or unusable.
wirksam or wirkung_unbekanntbeendetExpiry reached; the local safe fallback rule takes over.
beendetabgeschlossenEffect evidence or a documented investigation outcome is available.

geplant

Target
angenommen
Condition
Plant control confirms valid order.

geplant

Target
abgelehnt
Condition
Power, timing or a local limit conflicts with the command.

angenommen

Target
wirksam
Condition
Appropriate valid measurement proves the agreed effect.

angenommen

Target
wirkung_unbekannt
Condition
Measurement is missing or unusable.

wirksam or wirkung_unbekannt

Target
beendet
Condition
Expiry reached; the local safe fallback rule takes over.

beendet

Target
abgeschlossen
Condition
Effect evidence or a documented investigation outcome is available.

Reserve flexibility

Reserve flexibility

Check overlapping commitments against availability atomically.

30 and 40 kW compete for 50 kW.

The second commitment does not go beyond the scope.

Alternative considered
Independent planning lists overbook the plant.
Trade-off
Time window checks are becoming more complex.
Reassess
Many partial retrievals justify an extended model.

Terms in this step

Reserve flexibility
The second commitment does not go beyond the scope.

Try it yourself

Reserve 30 and 40 kW concurrently from 50 kW. State the outcome in both orders and the remaining capacity.

A hint for your attempt

Use the specific entities and conditions from this step. The two solution parts distinguish the decision from its evidenced outcome.

Compare with a possible solution
First part of the solution
30 kW first: 20 kW remain, 40 kW is rejected.
Second part of the solution
40 kW first: 10 kW remain, 30 kW is rejected. A simultaneous promise of 70 kW violates the rule.

Apply to your project

Which corresponding assumption would you check first in your project when many partial dispatches justify a richer model?

Step 6 examines: keep the measurement path separate.